The garage ceiling/gameroom floor had no insulation but now it has a 2 inch coat of closed cell urethane foam. Insulates and seals out air infiltration in a single step. I also foamed up all the exterior wall penetrations in the SIPs. And the drywall was delivered today. Sheetrocking starts tomorrow! It will look like a real house by the weekend.
Thursday, February 25, 2010
Thursday, February 18, 2010
Friday, February 12, 2010
02-12-2010 Interior Framing, Plumbing, AC Finished
The framers finished up everything on their list. They added the pocket door frames and the Jacuzzi tub surround. (Yes, it will be Jacuzzi brand!) The plumbers are finished with their "top out" and the AC contractor has installed the air handler and all the ducts. It looks like a giant silver spider in the attic.




And then when the electrician was supposed to show up... Old Man Winter showed up instead.
And then when the electrician was supposed to show up... Old Man Winter showed up instead.
Popout Bay Windows and the Porch 02-11-2010
Front Siding and Kids Tub 02-05-2010
The framers are finishing up work on the front of the house and the plumbers have installed the kids tub/shower combo. They had to knock some of the studs out of the way to get it in.
Wednesday, February 3, 2010
Right Front Gable 02-01-2010