Sunday, December 13, 2009

Final Grading Complete 12-12-2009

Progress is slow due to scheduling conflicts between the subcontractors but there is progress nonetheless. The pest subcontrol contractor has sprayed the foundation area with 100 gallons of Bifen pesticide. All I had to do was call them, they went out the next day and I paid them the following day. By far the easiest part of this job!



The foundation contractor has reformed the footings and graded the foundation so it will be the proper thickness. They still need to cover the soil with polyethelene plastic to prevent soil moisture from entering the slab and add the post-tension cables.

The blue skies and green pastures of summer are gone but the red and blue of PEX piping is in full bloom on our jobsite. The foundation is scheduled to be poured on Wednesday 12/16. Let's see if that comes to pass.